The Minister of Power, Mr Abubakar Aliyu  says that the  Zungeru Hydroelectric Power Plant in Niger state has injected  700 Megawatts(MW) to the National Grid to boost electricity.

Aliyu stated this during a farewell  party  for him and the Minister of State, Mr Goddy Jedy-Agba by the Ministry of Power on Friday in Abuja.

He said “Today the Zungeru Hydroelectric Power Plant has become a reality; we have as of today joined the grid with 700MW.

  Testing started Wednesday night.

“Information has reached us with the pictorial view of the meters showing us that the 700MW has gone on the grid , ‘’he said.

The minister said that the Kashimbila Hydroelectric Power Project, a joint project with the ministry of water resources, had been completed.

He said phase one of the project, which is the line taking electricity to Yandev in Benue over 240 kilometers, had been completed and  inaugurated last week.

On the Siemens project, Aliyu said that the ministry had installed transformers in Abuja, Ajah, Lagos, adding that 10 massive mobile substations had been cleared.

“ We have 10 of them at the port and the first one is in Ajah sub-station and some are also on the sea coming, ‘’ he said.

Aliyu also said that the ministry of power on Wednesday presented to the Federal Executive Council (FEC), a contract for over 13, 000kilometers distribution line.

He said that the contract was approved for the Presidential Power Initiative (PPI).

“One thing we should have in our minds is that these things don’t happen just at once, it is a process. These bring about delay of some of the projects, ‘’he said.

The minister urged all players in the industry to continue to work together in synergy to be able to achieve the desired results.

According to him, electricity is a value chain from generation to distribution, urging players to work in synergy.

Aliyu commended members of staff of the ministry and stakeholders in the sector, for the cordial working relationship.

He said that the ministers would not have achieved what they achieved without the support of the staff of the ministry.

Also speaking, the Minister of State for Power, Jedy-Agba also thanked the staff for the working relationship that existed between them.

“It is a long journey but I enjoyed working with you all as you took directives from us and you implemented them, ‘’ he said. (NAN)

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Business News

Edun Seeks Liquidity for Power Sector as NDPHC Declares Calabar Best Power Plant

Published

on

Share

By Eze Okechukwu, Abuja

The Minister of Finance and Coordinating Minister for the Economy, Wale Edun yesterday declared that liquidity was the major hindrance required by the troubled power sector to achieve the desired result of producing steady Power in Nigeria.

This is as the Managing Director of Niger Delta Power Holding Company (NDPHC) Chiedu Ugbo informed the Senate Committee on Power in Abuja yesterday that the Calabar Power Generation Company under its ownership was the best performing power plant in the country.

In his submission to the Committee investigating the controversial Make up Gas (MUG) Reprocessing Deal Involving the Ministry of Finance, NDPHC, Calabar Generation Company Limited and ACUGAS Limited, the Minister of Finance pointed out that the need for liquidity into the Power Sector remained the key to unlocking it.

The Minister who made the submission through his Special Assistant, Mallam Dahiru Moyi said the agreements on Gas supply between NPDHC and ACUGAS Limited was inherited by former President Muhammadu Buhari in 2015, following after the agreement was signed in 2011 during President Goodluck Jonathan’s administration.

According to him, “just as the Ministry of Justice was not aware of the contract agreement, the Ministry of Finance was also not part of it from the beginning but since government is a continuum, the Ministry of Finance later came into it for the purpose of facilitating the required liquidity.

“The issues on ground about contracts agreements being investigated by the Senate Committee on Power is not about restructuring but providing the required liquidity which the Ministry of Finance is doing through collaboration with the Nigerian Liquified Natural Gas (NLNG).

 “Since NLNG pays Gas in Dollars, the Ministry is collaborating with it for a practical solution of bringing liquidity into the age long contract agreement through Deed of Transfer.

“Make Up Gas (MUG) belongs to Calabar, Calabar belongs to NDPHC and NDPHC belongs to Federal and State governments with the Federal Government having 52.68%”, he said.

In his own submission before the Committee, the Managing Director of NDPHC, Chiedu Ugbo said the company as a result of the Gas supply agreement with ACUGAS Limited was taking Gas from three out of five units and generating power from Calabar plant to the National Grid which according to him was the best power plant in the entire country.

He said NDPHC went out of its way to construct an 80 kilometres gas pipeline for utilization of MUG in Calabar and Alaoji power plants.

He however lamented that problems relating to systemic transition, frequency and voltage issues have not made the firm achieve the desired results.

In his remarks, the Chairman of the Committee, Senator Enyinnaya Abaribe (APGA, Abia South) thanked the stakeholders for giving the Committee clarity on the issue but added that it was still an ongoing investigation.

Continue Reading

Energy and Power

Oil, Electricity Workers’ Unions Mobilise for Planned Strike

Published

on

Share
The Nigeria Union of Petroleum and Natural Gas Workers (NUPENG) has directed its members to comply with the directive of the two labour centres to begin an indefinite nationwide strike on Monday.

Its General Secretary, Mr Afolabi Olawale, in a statement on Saturday, said the union was committed to ensuring total compliance with the directive.

Recall that the Nigeria Labour Congress (NLC) and Trade Union Congress of Nigeria (TUC) declared an indefinite nationwide strike to begin on Monday, to express their grievances over the proposed new minimum wage.

.

In a joint statement signed by NLC President, Mr Joe Ajaero and TUC President, Mr Festus Osifo, the centres declared the strike over the tripartite committee’s inability to agree on a new minimum wage and the hike in electricity tariff.

Afolabi said the union was concerned and disturbed with the insensitive attitude of the federal government “to the very critical issue of negotiating a new minimum wage for Nigerian workers”.

“This is in view of the various socio- economic policies of this administration that have impoverished the working people of this country.

“Leaders of our great union at all levels, from the units, zones and branches, should immediately put all processes in place to ensure total compliance with this directive.”

Also, the National Union of Electricity Employees (NUEE) said it was mobilising its members to embark on the strike following the directive of NLC and TUC.

The Acting. General Secretary, Mr Dominic Igwebike, gave the directive to the members in a statement.

Igwebike said that along with the reasons of inconclusive negotiations on the minimum wage and electricity tariff hike, apartheid categorisation of Nigeria electricity consumers into bands was another, to embark on the strike.

“Given the above, all national, state, and chapter executives are requested to start the mobilisation of our members in total compliance with this directive to ensure the government does the right thing as stated above.

“The withdrawal of services becomes effective on Sunday 2nd June by 12.00 midnight, “ the union leader said. (NAN)

Continue Reading

Business News

FG Secures $500m World Bank Loan to Boost Electricity Distribution

Published

on

Share

By Tony Obiechina, Abuja 

In a strategic move to address the identified gaps in the Electricity Distribution Companies (DisCos), the Federal Government has secured a $500 million loan from the World Bank.

In a statement by Head of Public Communications, Bureau of Public Enterprises ((BPE) Amina Tukur Othman on Thursday, approval for the facility was given by World Bank Board of Directors on February 4, 2021.

According to the statement, “this funding supports the Nigerian Distribution Sector 

Recovery Program (DISREP) aimed at improving the financial and technical 

performance of the DisCos”.

The Distribution Sector Recovery Program is designed to enhance the 

financial and technical operations of the DisCos through capital investment and 

the financing of key components of their Performance Improvement Plans (PIPs), 

which have been approved by the Nigerian Electricity Regulatory Commission 

(NERC).

 

Key areas of improvement include:

• Bulk procurement of customer/retail meters and meter data 

management systems.

• Implementation of a Data Aggregation Platform (DAP).

• Strengthening governance and transparency within the DisCos.

• Program Components

• The DISREP comprises two main components:

• Program for Results (PforR):

• Allocation: $345 million

• Purpose: Support the implementation of selected PIP components.

Others include 

• Implementation: Bureau of Public Enterprises (BPE)

• Investment Project Financing (IPF):

• Allocation: $155 million

The Purpose is to finance the procurement of meters, a Data Aggregation 

Platform, and Technical Assistance.

The DISREP loan, particularly the Investment Project Financing (IPF) component, is expected to significantly benefit the Nigerian Electricity Supply Industry (NESI) by:

• Closing the metering gap

• Reducing Aggregate Technical, Collection, and Commercial (ATC&C) 

losses

• Improving remittances and liquidity for the DisCos

• Enhancing the reliability of power supply

• Increasing transparency and accountability within the DisCos.

The $500 million DISREP loan from the World Bank offers concessional financing 

with more favorable terms than commercial bank loans. This will enable the DisCos to:

1. Invest in critical distribution infrastructure.

2. Improve ATC&C losses.

3. Increase power supply reliability.

4. Achieve financial sustainability in the power sector.

5. Enhance transparency and accountability.

The statement further explained that significant progress has been made in the preparation of the DISREP Program, with several key milestones achieved, and approval by the Federal Executive 

Council (FEC) on August 3, 2022. execution of the Financing Agreement by the 

Federal Ministry of Finance, Budget and National Planning, and the World Bank, 

adoption of the Program Operations Manual (POM) by BPE and TCN, obtained 

Legal Opinion from the Attorney-General of the Federation, Execution of the 

Subsidiary Loan Agreement, effective declaration of the DISREP Program on 

January 31, 2023, inauguration of the DISREP Technical Committee on May 6, 

2024, inclusion in the Federal Government Borrowing Plan, approved by the 

Senate Committee on May 16, 2024.

To ensure repayment assurance, the Bureau of Public Enterprises sought and 

obtained approval from the Nigerian Electricity Regulatory Commission (NERC) 

and the National Council on Privatisation (NCP) for a structured repayment 

hierarchy. 

The structure prioritizes payments including, Statutory Payments (Taxes), Repayment of CBN market loans, Market obligations , Repayment of DISREP loan and DisCos’ net revenue.

This structured repayment plan aims to mitigate risks associated with repayment 

uncertainty and defaults, with regulatory sanctions imposed for any defaults.

Continue Reading

Read Our ePaper

Top Stories

SPORTS2 minutes ago

I Want to Play in EPL, Super Eagles’ forward says

Share Super Eagles and Genk of Belgium striker, Tolu Arokodare, says it has always been his dream to play in the...

DEFENCE17 minutes ago

Zulum Offers N5m Each to Families of 8 Slained CJTF Members 

Share Gov. Babagana Zulum of Borno has donated N5 million each to the families of eight members of Civilian Joint Task...

Uncategorized24 minutes ago

France to Partially Ban Smoking in Public Areas to Protect Children

Share France is to ban smoking in public outdoor spaces, including beaches, parks, school zones, bus stops and sports facilities starting...

CRIME32 minutes ago

Police Evacuates Remains of Bolt Driver Shot Dead in Yenagoa

SharePolice  operatives from the Bayelsa command have evacuated the remains of a bolt driver, who was shot dead on Friday...

Foreign News41 minutes ago

Comedian Russell Brand Pleads not Guilty to Rape, Sexual Assault

ShareBritish comedian and actor Russell Brand has pleaded not guilty to charges of rape and sexual assault. The 49-year-old appeared...

General News50 minutes ago

Tinubu Congratulates Chimaroke Nnamani on 65th Birthday 

SharePresident Bola Tinubu rejoices with Sen. Chimaroke Nnamani,  a former governor of Enugu State, as he celebrates his 65th birthday...

CRIME2 hours ago

Court Remands 18-year-Old Student for Alleged Murder 

ShareA Makurdi Chief Magistrates’ Court on Friday ordered the remand of an 18-year old student, Joseph Chive, at a Makurdi...

CRIME2 hours ago

Man Jailed 14 years for Attempted Sexual Assault on Minor

ShareAn Ikeja Sexual Offences and Domestic Violence Court on Friday sentenced a man, Damilare Adewale to 14 years imprisonment for...

Foreign News3 hours ago

Man Sentenced for Blackmailing German Priest With Nude Photos

Share A 50-year-old man was on Friday given a 20-month suspended sentence for blackmailing a German priest with nude photos. During...

community4 hours ago

Domestic Chores Not for Females Alone- Residents

Share Some residents of Karu Local Government Area of Nasarawa State have advised both men and women to support each other...

Copyright © 2021 Daily Asset Limited | Powered by ObajeSoft Inc